LAKE DALLAS ROAD WORK . com
HUNDLEY DR & SHADY SHORES RD
CONSTRUCTION UPDATES
DDM Construction Corp is delivering critical infrastructure improvements at Hundley Dr & Shady Shores Rd in Lake Dallas. Work includes new water lines, sanitary sewer lines, and storm drainage along Hundley Dr, Shady Shores Rd, and Beck Ave.
Construction is anticipated March 2026 through March 2028 and will occur in phases, so not all areas will experience construction at the same time. Updates will be posted as each phase begins.
Check below for project updates, including traffic pattern changes and construction progress.
We look forward to delivering improvements the City of Lake Dallas, its residents, and visitors can enjoy.


Latest Update
Central Hundley (Shady Shores Rd to Lakeview Dr)
OCT 16 2026
Construction Updates
- Between Atchison Dr. and Lakeview Dr., weather and conditions permitting, Hundley Dr. will remain one-way westbound while the roadway is paved one half at a time. We anticipate restoring two-way traffic in this section by mid-November.
- Sidewalk construction, now including pedestrian ramps, is still scheduled to be completed by mid-November, pending any weather-related delays.
- Finish-out activities will continue through the end of 2026, including streetlights, irrigation, landscaping, pavement markings, and permanent signage. This work will progress in phases and must be completed in a specific sequence, so there may be days when crews are not visibly working onsite. However, aside from weather impacts, we are currently experiencing no significant delays. Central Hundley remains an active priority, and we will continue working to complete the remaining improvements as quickly as feasibly possible.
West Hundley (Lake Dallas Dr to Shady Shores Rd)
- Hundley Dr. will remain one-way westbound, regardless of which side of the roadway traffic is shifted to, until construction between Shady Shores Rd. and Lake Dallas Dr. is complete.
- South-side construction is anticipated to continue for approximately two more weeks, pending weather.
- Once the south-side concrete is ready for traffic, the Shady Shores Rd./Hundley Dr. intersection will be closed overnight so the intersection can be lowered several feet to its new elevation. The following day, long-term asphalt pavement will be installed to provide a durable, all-weather driving surface until the intersection is permanently paved with concrete several months from now as part of the Shady Shores paving work.
- Please avoid the intersection while this work is taking place. Advance notice will be provided on message boards several days before the closure.
- Once the intersection asphalt is complete, traffic on West Hundley will shift to the south side of the roadway while remaining one-way westbound. North- side construction will then begin. The full roadway, including driveways, is anticipated to be paved by mid-December, pending weather. Once paving is complete, two-way traffic will resume.
- Finish-out activities are anticipated to begin in mid-December and continue through the end of January, pending weather. This work includes sidewalks, streetlights, irrigation, landscaping, pavement markings, and permanent signage. Similar to Central Hundley, this work will progress in phases and may appear slower at times due to the sequencing required.
Beck Ave
- Sewer & Water line installation complete.
- Utility work is taking place on Wildwood & Columbia now. Once the water installation is complete (tentatively late October), testing will begin. Once water line testing has passed, services on Beck will be tied-in to the new water line.
- Road reconstruction is anticipated to start mid-November and last through end of February (pending weather).
South Shady Shores (Main St to Hundley Dr)
- Utilities have begun. Upon water line completion, we will install sewer, then storm drain. Utilities expected to be complete by end of November (pending weather).
- The East half of South Shady Shores was milled this week in preparation for shifting traffic to the West half of the road so that the sewer line can be installed on the East side. This is anticipated to happen mid-next week.
- Shady Shores is planned to be done (earthwork & paving) in halves, so that one-way Northbound traffic can be maintained.
East Hundley (Lakeview Dr to Willow Grove Park)
- When construction begins on East Hundley (tentatively beginning of November - pending weather), traffic is planned for one-way Eastbound traffic for the duration of construction (utilities through paving completion).
- Full timeline of East Hundley construction is expected to be November 2026 through May 2027 (pending weather).
- More details to come as this work approaches.
North Shady Shores (Hundley Dr to Swisher Rd)
- Work expected to begin February 2027.
- As this work approaches, more details will be provided.
West Hundley Paving Plan
The drawing below is provided as a reference to the street paving being done on Hundley between Shady Shores & Lake Dallas Dr. THESE PAVING AREAS ARE SUBJECT TO CHANGE. Regardless of half, traffic will stay one-way Westbound in this area.
South Half
1. Brown areas will be paved. Yellow will be access points during this time.
2. Yellow area will be paved. Brown will be access points during this time.
North Half
3. Pink areas will be paved. Green will be access points during this time.
4. Green area will be paved. Pink will be access points during this time.
As stated above, the intersection of Hundley/Shady Shores will be dropped to new elevation once the South half is ready for traffic. Official date of this work will be posted onsite via message board once the date is confirmed.


Traffic Control Plan
Hundley Dr is currently undergoing construction, necessitating strict traffic control measures and detours. Current detour routes utilize Swisher Rd and Main Street to bypass Hundley. Hundley is one-way Westbound between Shady Shores Rd and Lake Dallas Dr. Shady Shores is also under construction between Main St & Hundley Dr. Current detour routes utilize Lake Dallas Dr and Gotcher Ave to bypass Shady Shores. We recommend that commuters plan for an additional 5-10 minutes of travel time during peak hours. See maps showing closures (red areas) and designated detour routes (in pink arrows).


Resident Inquiries
For questions or feedback regarding the Hundley Dr & Shady Shores Rd project, please fill out this form!