Previous Updates Archive

This page serves as a historical record for the Hundley Dr & Shady Shores Rd Project. Below, you will find archived updates from previous phases of construction, maintaining a transparent timeline of our progress and critical infrastructure improvements in Lake Dallas.

Previous Updates

MAR 9 2026

Contract Time Has Begun!

As you may have noticed, utility relocations have been taking place on Hundley Dr over the past couple of weeks. Starting later this week, Hundley Dr will be transitioned to one-way Westbound from Lakeview Dr to Lake Dallas Dr so that we can begin installing new water line in the area.

​

Eastbound traffic will be detoured around Hundley Dr via two options:

     1. Lake Dallas Dr -> I35E Frontage Rd -> Swisher Rd -> Lakeview W -> N Lakeview Dr

     2. Lake Dallas Dr -> Main St -> Thompson Dr -> S Lakeview Dr

​

Lake Dallas Middle School traffic may access the school via Falcon Dr or Lakeview Dr but must exit the school heading Westbound on Hundley Dr.

(Oldest at Top, Newest at End)

Due to the utility work taking place along Hundley Dr, intermittent closures will be taking place on Gotcher Ave, and a full closure on Falcon Dr starting tomorrow (3/24/2026). Below is a snip of these closures for reference!

MAR 23 2026

Gotcher Ave & Falcon Dr Closures
Screenshot 2026-03-23 164627.png

APR 06 2026

Pending weather delays, Beck is scheduled to begin utility work on April 9, 2026. During this time, traffic will be limited to one-way around the work zone. Parking will not be allowed on Beck Ave during construction due to the limited width of the roadway.

​

Falcon Dr closure has been delayed due to resequencing of work. At this point in time, Falcon Dr closure has not pffocially been scheduled, but updates will follow!

Beck Ave Utility Work & Falcon Updates

APR 28 2026

Due to weather and required phasing changes, Beck Ave utility work has been rescheduled to a later date. Notices will be sent to property owners on Beck Ave, Wildwood Dr, and Columbia Cir when this work is rescheduled.

 

Falcon Dr storm drainage has been installed, and Falcon Dr will remain open until road reconstruction begins at a later date.

 

Water line installation on Hundley Dr, from Lakeview Dr to Lake Dallas Dr, is nearing completion. Installation is expected to finish by the end of this week, pending any additional weather delays. Following installation, we will begin testing, disinfection, and tie-in/connection to the new water line. This phase is expected to take a couple of weeks.

 

Sanitary sewer installation from Gotcher Ave to Lake Dallas Dr is beginning this week. This work is expected to take approximately three weeks, barring any weather delays. The current traffic pattern will remain in place during this work. Hundley Dr will remain one-way westbound from Lakeview Dr to Lake Dallas Dr. Any additional traffic control closures are due to Atmos gas relocations, which are not associated with this project.

 

Looking ahead, Hundley Dr will be fully closed from Atchison Dr to Shady Shores Rd once school is out for summer (starting 5/26/26). This full closure is required to install the new storm drainage system beneath Hundley Dr in this section. Our goal is to fully reopen Hundley Dr to traffic in this area before the start of school (8/12/26). At a minimum, Hundley Dr will return to one-way westbound traffic when school resumes in August. We anticipate Hundley Dr will be fully restored—from Lakeview Dr to Lake Dallas Dr (including sidewalks, landscaping, etc.)—by the end of 2026.

Project Update - 4/28/2026

Water line installation is complete on Hundley Dr. We are currently performing bacteriological testing on the newly installed system. Once passing samples are received, we will begin connections and service tie-ins to the new water system. Most of this work will be performed at night to minimize disruption to residents’ daily routines as much as possible. Paper notices will be distributed alerting residents of when a water shutdown is scheduled. Shady Shores water line will not begin for a few months.

 

Sanitary sewer installation from Gotcher Ave to Lake Dallas Dr is ongoing and nearing completion. This week, we are scheduled to begin sanitary sewer installation from Lakeview Dr to Atchison Dr.

 

You may have noticed concrete pipe arriving onsite. Once sanitary sewer installation is complete, we will begin installing the new underground storm sewer system along Hundley Dr from Lakeview Dr to Lake Dallas Dr. During this phase of work, Hundley Dr will be fully closed from Atchison Dr to Shady Shores Rd.

 

We originally planned to implement this full closure once school was out for the summer; however, the significant amount of rainfall received over the past several weeks has delayed the start of this phase. Please refer to our previous update for additional information regarding the planned reopening of Hundley Dr.

 

We appreciate everyone’s continued patience as we work through ongoing weather impacts and schedule delays caused by repeated rainfall events. Our crews are continuing to work wherever conditions allow in order to keep the project moving forward safely and efficiently. Until the full closure is implemented, the current detour routes shown in the section below remain active and valid.

MAY 27 2026

Project Update - 5/27/2026

Hundley Dr is officially closed from Lakeview Dr to Shady Shores Rd. Business access remains on the East side of Hundley (via Lakeview). School traffic can access via Falcon Dr, and park traffic can access via Gotcher Ave. This closure is necessary for us to install the underground storm drain beneath Hundley Dr as we try to complete the new concrete paving on Hundley Dr prior to the start of school in August.

​

During this closure, Shady Shores Rd will remain open in both directions. Outside of the original detours (as shown below), Shady Shores Rd can also be used as a detour route to bypass Hundley Dr.

JUNE 3 2026

Hundley Dr Officially Closed!

Hundley Dr has been fully closed to traffic between Atchison Dr and Shady Shores Rd since 6/3/26. At this time, all sanitary sewer work has been completed, water tie-ins and final connections are taking place {see below for further details on this}, and storm sewer installation is wrapping up.
 
The next big phase we are entering now is the earthwork and paving phase. This week we began excavation to drop Hundley Dr to its new elevation. By the end of next week, concrete paving operations will begin. Our goal has been to have Hundley Dr open to traffic by the start of school (August 12th) and this is still our goal and expectation, despite the rain delays! 

JULY 15 2026

Hundley Dr Construction Update

Traffic Changes Upcoming
  • Overnight on 7/22 (8 PM to 6 AM) and 7/23 (8 PM to 6 AM) the intersection of Shady Shores & Hundley will be fully closed while we complete all underground utility installation in the intersection. During these overnight hours, traffic that needs to get onto Hundley between Shady Shores & Lake Dallas Dr (the railroad tracks) will be able to access from Lake Dallas Dr.
    ​

  • Hundley Dr will remain closed between Atchison Dr & Shady Shores Rd until concrete paving completion, scheduled for the week of August 10th.
     

  • Outside of scheduled nightly changes (above), Hundley Dr will remain one-way Westbound traffic between Shady Shores Rd and Lake Dallas Dr.
     

  • Night work storm installation will start on 7/27, lasting for 2 weeks, while we complete the storm sewer installation on Hundley Dr between Shady Shores Rd & Lake Dallas Dr. 

Water Tie-Ins Remaining
  • Overnight on 7/26 (10 PM to 6 AM), the new water line on Hundley Dr will be tied into the South side of Shady Shores Rd. This tie-in will put all businesses/residents between Hundley Dr and Main St out of water during those hours.
     

  • ​Overnight on 7/28 (10 PM to 6 AM), the new water line on Hundley Dr will be tied into the North side of Shady Shores Rd. This tie-in will put all businesses/residents between Hundley Dr and Overly Dr (including Lake Haven Estates Mobile Home Park) out of water during those hours.

As of this today, Hundley Dr is open to one-way Westbound traffic from Lakeview Dr to Lake Dallas Dr. Once we have cure strength on the South side of Hundley Dr, Hundley Dr will resume two-way traffic between Lakeview Dr and Shady Shores Rd. We anticipate this to happen next Monday (8/17/2026).

West Hundley will remain one-way Westbound from Shady Shores Rd to Lake Dallas Dr until utilities and paving are completed in the stretch of Hundley Dr. This is anticipated for end of October (weather-dependent).

Utilities have officially started on Beck Ave. Beck Ave will be under construction from now until end of November (weather-dependent).

The next large phase of construction will be Shady Shores (from Main St to Hundley Dr) starting tentatively 9/2/2026.

AUG 12 2026

Hundley Dr Partially Open!!

Traffic Changes Upcoming
  • Night work storm installation will start on 8/17, lasting for 1 week, while we complete the storm sewer installation on Hundley Dr between Shady Shores Rd & Lake Dallas Dr.
  • ​Beck Ave access will be restricted over the next 3 months while utilities and paving work is taking place. Traffic will still be allowed in and out, we just asking that residents refrain from parking on the street so that there is an accessible driving lane.
  • Outside of scheduled nightly changes (above), Hundley Dr will remain one-way Westbound traffic between Shady Shores Rd and Lake Dallas Dr.
  • Once Shady Shores Rd construction begins, traffic will be limited to one-way. More details will follow once this next phase of construction is firmed up.

SEP 9 2026

Construction Updates

Central Hundley (Shady Shores Rd to Lakeview Dr)

-  Hundley will remain two-way traffic.​
-  Drainage inlet construction will continue until complete.
-  Driveways and side streets are scheduled to be fully complete by end of September.
-  Sidewalk construction is scheduled to start, upon resource availability, within the next couple of weeks.
-  Finish-Out activities will start to shape up through end of 2026 (street lights, irrigation system, landscaping, pavement markings & permanent signs).

West Hundley (Lake Dallas Dr to Shady Shores Rd)

-  Hundley will remain one-way Westbound traffic, despite which side of the road traffic is driving on.​
-  Earthwork and paving will start on the South side of Hundley this week. South side construction is anticipated to last 3 weeks, pending weather.
    - Driveway access will be limited to select driveways to speed up the earthwork and paving operation. Fewer leave-outs means quicker finish.
-  Once South side is complete, traffic will shift to South side (Westbound one-way) and North side construction will start. The full roadway is anticipated to be      fully paved by mid-November (pending weather), including completed driveways. Once Hundley is complete, traffic will resume to two-way.
-  Finish-Out activities will start mid-November and will continue through end of January (pending weather). This includes sidewalks, street lights, irrigation,          landscaping, pavement markings & permanent signs.

Beck Ave

-  Sewer installation complete.
-  Water line installation is starting this week and expecting to last through end of September (pending weather).
-  Road reconstruction is anticipated to start mid-October and last through end of November (pending weather).

South Shady Shores (Main St to Hundley Dr)

-  Utilities on Shady Shores is anticipated to start by end of September. We are scheduled to do water line, then sewer, then storm drain. Utilities expected to        be complete by end of November (pending weather).
-  Shady Shores is planned to be done (earthwork & paving) in halves, so that one-way traffic can be maintained.

East Hundley (Lakeview Dr to Willow Grove Park)

-  When construction begins on East Hundley (tentatively beginning of November - pending weather), traffic is planned for one-way Eastbound traffic for the        duration of construction (utilities through paving completion).​
-  Full timeline of East Hundley construction is expected to be November 2026 through May 2027 (pending weather).
-  More details to come as this work approaches.

North Shady Shores (Hundley Dr to Swisher Rd)

-  Work expected to begin February 2027.
-  As this work approaches, more details will be provided.

OCT 5 2026

Construction Updates

Central Hundley (Shady Shores Rd to Lakeview Dr)

-  Between Atchison Dr & Lakeview Dr, weather/conditions permitting, starting tentatively 10/6, Hundley will be one-way Westbound so that the road can be          paved (half at a time) in this area. 
-  Street paving from Atchison to Lakeview is scheduled to be fully complete by end of October, pending weather delays.
-  Sidewalk construction has started, and is scheduled to be completed (excluding ramps) mid-November, pending weather delays.
-  Finish-Out activities will start to shape up through end of 2026 (street lights, irrigation system, landscaping, pavement markings & permanent signs).

West Hundley (Lake Dallas Dr to Shady Shores Rd)

-  Hundley will remain one-way Westbound traffic, despite which side of the road traffic is driving on.​
-  South side construction is anticipated to last another 2 weeks, pending weather.
-  Once South side is complete, traffic will shift to South side (Westbound one-way) and North side construction will start. The full roadway is anticipated to          be fully paved by end of November (pending weather), including completed driveways. Once paving is complete, traffic will resume to two-way.
-  Finish-Out activities will start mid-December and will continue through end of January (pending weather). This includes sidewalks, street lights, irrigation,        landscaping, pavement markings & permanent signs.

Beck Ave

-  Sewer & Water line installation complete.
-  Utility work is taking place on Wildwood & Columbia now. Once the water installation is complete (tentatively 10/16), testing will begin. Once water line                testing has passed, services on Beck will be tied-in to the new water line.
-  Road reconstruction is anticipated to start early-November and last through end of December (pending weather).

South Shady Shores (Main St to Hundley Dr)

-  Utilities have begun. Upon water line completion, we will install sewer, then storm drain. Utilities expected to be complete by end of November (pending           weather).
-  Shady Shores is planned to be done (earthwork & paving) in halves, so that one-way Northbound traffic can be maintained.

East Hundley (Lakeview Dr to Willow Grove Park)

-  When construction begins on East Hundley (tentatively beginning of November - pending weather), traffic is planned for one-way Eastbound traffic for the        duration of construction (utilities through paving completion).​
-  Full timeline of East Hundley construction is expected to be November 2026 through May 2027 (pending weather).
-  More details to come as this work approaches.

North Shady Shores (Hundley Dr to Swisher Rd)

-  Work expected to begin February 2027.
-  As this work approaches, more details will be provided.

Central Hundley (Atchison Dr to Lakeview Dr) Paving Plan

The drawing below is provided as a reference to the street paving remaining on Hundley between Atchison and Lakeview. Regardless of half, traffic will be one-way Westbound in this area.

North Half
1. Brown areas will be paved. Yellow will be access point during this time.
2. Yellow area will be paved. Brown will be access points during this time.

South Half
3. Blue areas will be paved. Pink will be access point during this time.
4. Pink area will be paved. Blue will be access points during this time.

The intersection will remain existing until a later date, yet to be determined. There is still utility work to take place at this intersection. Once that utility work is complete. the intersection paving will be coordinated and scheduled.

East Central Hundley Paving Plan.png